First Gotherington embankment collapse contracts placed – and green light for Laverton!
article by: Ian Crowder
posted on: 18 August 2010
updated on: 22 November 2010
Earlier this month, the Gloucestershire Warwickshire Railway met
with its consulting engineers and the loss adjusters for our
insurers, Travelers. As a result, a final plan has been
developed for the embankment repairs and work is about to
start.
The project to rebuild the collapsed embankment, led by
properties director Darren Fairley, has been divided into seven
separate work packages appropriate to the movement and damage
found, and improved site drainage. Click here for an diagram and
explanation of the seven sections of work. The embankment will
stabilised and rebuilt using a blend of design options between soil
'nailing' the less damaged sections of the embankment and securing
them for the long term, and fully digging out and rebuilding where
damage is most severe.
Design of the work is almost complete. The railway's
consulting engineers, David Symonds Associates (the company that
advised on the Severn Valley Railway's devastating slips and our
previous repair to the Cheltenham Racecourse embankment) can now
provide a reasonably accurate indication of costs.
Drainage work starts now
Explains Malcolm Temple, chairman of GWSR Plc: "I'm delighted
that we have now negotiated access rights to the embankment with
the owner of the adjoining land. This will enable the heavy
plant and equipment to be used as well as the materials to be used,
to easily reach the site.
"In addition, tenders have been received for the new drainage
system on the Cotswold side of the line, which will better
intercept water coming off the hills than the original 1903 design
which has shown with dramatic effect to be no longer
adequate. New drains on both sides of the line (Malvern side
being incorporated with the main collapse repair), will direct the
flow more efficiently to two existing GWR-built culverts. We
now believe BR struggled with this location, particularly just
before closure of the railway. But since then, the problems have
laid dormant - until now.
"I'm glad to say that the winning tender for this work is lower
than the original budget and the contract has been placed for this
first stage of the work. Contractors should starting this
work by the end of the month.
"Tenders have also been received for the soil nailing*.
This is a modern technique that, as its name suggests, comprises
huge 'nails' that reinforce the strength of the embankment.
The nails extend right into the underlying ground to secure the
embankment slope by stopping further slippage and coming under
tension as they slightly bend"
Analysis of the considerable amount of slag and locomotive ash
that has been used for past repairs now appears not to be
contaminated or toxic as first thought. The ash, together
with unstable soil, will be excavated and the railway has received
tenders for this work. The final contract sum will be
negotiated as soon as the design work is finalised and that is
expected to take place soon.
Budget
In cost terms some real savings have been made from the original
£1.1 million cost estimate, as Malcolm explains. "This is
partly because the ash fill doesn't appear to be contaminated which
would have brought a significant additional cost for its safe
disposal. Although final detailed costings have yet to be
concluded, we are confident that the total bill won't exceed
£900,000. That's still an enormous sum, and it leaves at least
£400,000 to be found over and above the expected insurance claim
settlement.
"Although different contractors will be involved in the separate
elements of the work, these have been taken together for cost
purposes and I'm delighted to say that the Board has authorised the
main work to start from 1 October, after the essential drainage
work has finished.
"However, it is important to point out that funds must flow in
now, to ensure that the once the work starts, it will continue
through to completion. If we run out of money, then the work
will have to be suspended until the finance is available. If
the cash is available, the work is likely to be completed by May
2011 - and again, this is earlier than some estimates have
suggested."
The railway is about to start a major £1 million fund-raising
initiative. But if the cost is less than estimated, why so
much?
Malcolm explains: "One of the really attractive features of our
railway is that we have several miles of embankment that are in
some cases, very high. This allows for some of the finest
countryside views that you can see anywhere from a carriage window
and it is a bonus for railway photographers too, as pictures in the
railway press regularly show.
"The Board is very conscious that the collapse of the embankment
at Gotherington is a call to action for some other locations.
Once the contractors have completed the drainage work at
Gotherington, they will immediately focus on new drainage at Far
Stanley. Work during the 'close' season will also be carried
out at the so-called 'Chicken Curve' on the Toddington side of
Winchcombe station. The work includes reduction of the depth
and weight of ballast at this point."
Chicken Curve is a name given by railway volunteers because
there was a chicken farm adjacent to the curve (the old chicken
sheds are still there). It's definitely not because of any
thought of 'running the gauntlet' on any past track or embankment
issues!
Adds Malcolm, "the additional emergency funds will allow us to
ensure that the rest of our infrastructure is secure for future
generations to enjoy."
Malcolm also points out that discussions are taking place with
the insurers for compensation for lost income and other
costs. "Our passenger figures have held up well because of
the huge appeal of the GWR175 event - but because of the embankment
collapse our ordinary, day-to-day passenger traffic is about 25 per
cent down compared with last year. That coincides almost
exactly with the usual takings at Cheltenham Racecourse
station. If this claim is successful, it should ensure that
there is no impact on the profit & loss account from the
collapse."
Forging north
Malcolm says that the aim has been to ensure that the embankment
collapse at Gotherington doesn't affect the railway's overall
expansion programme. "I'm delighted to say that the temporary
hold on the Laverton extension has been lifted by the Board.
The Permanent Way team has now been asked to proceed as quickly as
they can towards completing this part of the project. Most of
the track is in place now and the team will press ahead with the
final work, including ballasting and installation of a run-round
loop.
"The plan is to have this work completed in time for next season
with trains running to Laverton loop from March 2011."
* What is soil nailing? It is a technique developed in France in
the 1970s and is now widely used throughout the world for civil
engineering projects. It has proven to be an extremely
effective way of stabilising and increasing the shear strength of
soil slopes such as cuttings, embankments and retaining
walls. Holes are drilled and slender threaded bars inserted,
usually with expanding 'plugs' that lock the bar into the
surrounding soil. The bore surrounding the rod is then grouted
which prevents corrosion and a large nuts are used to secure the
bars against large plates (or 'nail heads') on the slope surface
which tie in to geotechnical reinforcing grids where appropriate to
complete the repair. These are easily confused with, but not
the same as, anchors which are grouted up hard and tight and tie
sections of rock etc. together where they have become unstable.
8 comments for “First Gotherington embankment collapse contracts placed – and green light for Laverton!”
Comment on this item