GWR header image


 
Appeal banner

First Gotherington embankment collapse contracts placed – and green light for Laverton!


article by: Ian Crowder
posted on: 18 August 2010
updated on: 22 November 2010

/media/143962/dsc_0349_thumb.jpg/media/143969/dsc_0352_thumb.jpg/media/143976/dsc_0370_thumb.jpg/media/143983/dsc_0363_thumb.jpg/media/143990/dsc_0418_thumb.jpg/media/143997/dsc_0357_thumb.jpg

Earlier this month, the Gloucestershire Warwickshire Railway met with its consulting engineers and the loss adjusters for our insurers, Travelers.  As a result, a final plan has been developed for the embankment repairs and work is about to start.

The project to rebuild the collapsed embankment, led by properties director Darren Fairley, has been divided into seven separate work packages appropriate to the movement and damage found, and improved site drainage. Click here for an diagram and explanation of the seven sections of work. The embankment will stabilised and rebuilt using a blend of design options between soil 'nailing' the less damaged sections of the embankment and securing them for the long term, and fully digging out and rebuilding where damage is most severe. 

Design of the work is almost complete.  The railway's consulting engineers, David Symonds Associates (the company that advised on the Severn Valley Railway's devastating slips and our previous repair to the Cheltenham Racecourse embankment) can now provide a reasonably accurate indication of costs.

Drainage work starts now

Explains Malcolm Temple, chairman of GWSR Plc: "I'm delighted that we have now negotiated access rights to the embankment with the owner of the adjoining land.  This will enable the heavy plant and equipment to be used as well as the materials to be used, to easily reach the site.

"In addition, tenders have been received for the new drainage system on the Cotswold side of the line, which will better intercept water coming off the hills than the original 1903 design which has shown with dramatic effect to be no longer adequate.  New drains on both sides of the line (Malvern side being incorporated with the main collapse repair), will direct the flow more efficiently to two existing GWR-built culverts.  We now believe BR struggled with this location, particularly just before closure of the railway. But since then, the problems have laid dormant - until now. 

"I'm glad to say that the winning tender for this work is lower than the original budget and the contract has been placed for this first stage of the work.  Contractors should starting this work by the end of the month.

"Tenders have also been received for the soil nailing*.  This is a modern technique that, as its name suggests, comprises huge 'nails' that reinforce the strength of the embankment.  The nails extend right into the underlying ground to secure the embankment slope by stopping further slippage and coming under tension as they slightly bend"

Analysis of the considerable amount of slag and locomotive ash that has been used for past repairs now appears not to be contaminated or toxic as first thought.  The ash, together with unstable soil, will be excavated and the railway has received tenders for this work.  The final contract sum will be negotiated as soon as the design work is finalised and that is expected to take place soon. 

Budget

In cost terms some real savings have been made from the original £1.1 million cost estimate, as Malcolm explains.  "This is partly because the ash fill doesn't appear to be contaminated which would have brought a significant additional cost for its safe disposal.  Although final detailed costings have yet to be concluded, we are confident that the total bill won't exceed £900,000. That's still an enormous sum, and it leaves at least £400,000 to be found over and above the expected insurance claim settlement.

"Although different contractors will be involved in the separate elements of the work, these have been taken together for cost purposes and I'm delighted to say that the Board has authorised the main work to start from 1 October, after the essential drainage work has finished.

"However, it is important to point out that funds must flow in now, to ensure that the once the work starts, it will continue through to completion.  If we run out of money, then the work will have to be suspended until the finance is available.  If the cash is available, the work is likely to be completed by May 2011 - and again, this is earlier than some estimates have suggested."

The railway is about to start a major £1 million fund-raising initiative.  But if the cost is less than estimated, why so much?

Malcolm explains: "One of the really attractive features of our railway is that we have several miles of embankment that are in some cases, very high.  This allows for some of the finest countryside views that you can see anywhere from a carriage window and it is a bonus for railway photographers too, as pictures in the railway press regularly show.

"The Board is very conscious that the collapse of the embankment at Gotherington is a call to action for some other locations.  Once the contractors have completed the drainage work at Gotherington, they will immediately focus on new drainage at Far Stanley.  Work during the 'close' season will also be carried out at the so-called 'Chicken Curve' on the Toddington side of Winchcombe station.  The work includes reduction of the depth and weight of ballast at this point."

Chicken Curve is a name given by railway volunteers because there was a chicken farm adjacent to the curve (the old chicken sheds are still there).  It's definitely not because of any thought of 'running the gauntlet' on any past track or embankment issues!

Adds Malcolm, "the additional emergency funds will allow us to ensure that the rest of our infrastructure is secure for future generations to enjoy."

Malcolm also points out that discussions are taking place with the insurers for compensation for lost income and other costs.  "Our passenger figures have held up well because of the huge appeal of the GWR175 event - but because of the embankment collapse our ordinary, day-to-day passenger traffic is about 25 per cent down compared with last year.  That coincides almost exactly with the usual takings at Cheltenham Racecourse station.  If this claim is successful, it should ensure that there is no impact on the profit & loss account from the collapse."


Forging north

Malcolm says that the aim has been to ensure that the embankment collapse at Gotherington doesn't affect the railway's overall expansion programme.  "I'm delighted to say that the temporary hold on the Laverton extension has been lifted by the Board.  The Permanent Way team has now been asked to proceed as quickly as they can towards completing this part of the project.  Most of the track is in place now and the team will press ahead with the final work, including ballasting and installation of a run-round loop.

"The plan is to have this work completed in time for next season with trains running to Laverton loop from March 2011."

* What is soil nailing? It is a technique developed in France in the 1970s and is now widely used throughout the world for civil engineering projects.  It has proven to be an extremely effective way of stabilising and increasing the shear strength of soil slopes such as cuttings, embankments and retaining walls.  Holes are drilled and slender threaded bars inserted, usually with expanding 'plugs' that lock the bar into the surrounding soil. The bore surrounding the rod is then grouted which prevents corrosion and a large nuts are used to secure the bars against large plates (or 'nail heads') on the slope surface which tie in to geotechnical reinforcing grids where appropriate to complete the repair.  These are easily confused with, but not the same as, anchors which are grouted up hard and tight and tie sections of rock etc. together where they have become unstable.







8 comments for “First Gotherington embankment collapse contracts placed – and green light for Laverton!”

  1. Gravatar of Rodger NagleRodger Nagle
    Posted 19 August 2010 at 11:52:12

    Great to see that a permanent solution is being implemented that will give this section of the line a long future. I am also encouraged by the proactive stance being taken by the railway in ensuring other potential problems are being addressed. These together with the push to Laverton will provide a fantastic "relaunch" of the line next spring. I have no doubt that a spectacular event is being planned to celebrate.
    I hope to be back in the UK next August (my father in law will be 80 and lives in Aston Somerville) and look forward to travelling the whole line.
    Rodger Nagle - Melbourne

  2. Gravatar of andy bryneandy bryne
    Posted 19 August 2010 at 15:04:40

    Many thanks again for a very detailed and informative update on a very significant difficulty for the GWR and one that the GWR has tackled with great professionalism (in my view). It is excellent news that work can now start very soon and also good news that the northern extension is now restarting. I am particularly anxious for Broadway Stn to reopen soonest as it will knock 5 miles off my journey to the railway!

  3. Gravatar of Darren FairleyDarren Fairley
    Posted 20 August 2010 at 14:14:30

    Rodger, thanks for flying the GWR flag so far away, look forward to welcoming you back to the whole line!

    Andy many thanks. Keep an eye on the website, there are some exciting developments happening at Broadway - the Broadway Pioneers have been very busy over the last few months and plans are developing nicely too.

  4. Gravatar of John McMillanJohn McMillan
    Posted 24 August 2010 at 17:48:16

    The detailed explanations of the work on the slip are first class, and nobody should be complaining about a lack of information. I have one slight worry however; the running line has a 20mph TSR in force at present, and P-Way are working hard to fettle the line, but are suddenly told to go all out for Laverton. I'm sure laying an extension is more exciting than dealing with dipped joints, but shouldn't we have the existing line brought back to top standard before laying more? Rest assured I'm longing to see the line open to Laverton, but might we be in danger of taking our eye off the ball?

  5. Gravatar of Darren FairleyDarren Fairley
    Posted 25 August 2010 at 21:04:25

    Interesting issue raised about taking eye off the ball - though most of our visitors would not be aware of the speed restriction. To aliveate concerns and to quickly explain, the Gala and increased working with top and tailing locos due to the collapse at Gotherington, has increased work to maintain the railway hence the current speed restriction to ease the wear a little whilst the dipped joints are tackled.

    However if anyone gets the chance to look through the affiliated sites, Nigel Blacks updates (From Broadway Extension link) Im sure would demonsrate the eye is well on the ball.

    Whilst it is affiliated with the extension, Nigels updates show just as much about the maintenance on the running section as the extension.

    The gang(s) are using some really good and neat new equipment for stone blowing dipped joints, not to mention the road-rail landrover and tamper (a very rare piece of kit a preserved railway), and they are making headway at improving the ride, which is already noticeable - even from the rather lovely and soft cushions on our MK1 seats!!!!

    Its a busy time to say the least at the moment......

  6. Gravatar of Malcolm TempleMalcolm Temple
    Posted 25 August 2010 at 21:39:51

    The Board's strategy for the present line is quite clear. As soon as we are at Laverton all attention and budget switches to the existing line until it is to satisfactory standards

  7. Gravatar of Howard ParkerHoward Parker
    Posted 30 August 2010 at 23:05:26

    I think the strategy the Board has been following continues to be excellent and to be applauded. Life everywhere these days seesm to be teaching us to do things properly and get back to the basics and I guess these P-way issues are teaching us to get the foundations of our railway right and not to get too carried away by our more ambitious plans for expansion.

    I cant help wondering, though: are there any plans for a bit of double track somewhere on the line - Toddington to Winchcombe springs to mind? I know this is hugely expensive and might be considered a luxury, particularly in light of current concerns and priorities, but even a short section would be a huge draw for people who want to be able to recreate a GWR mainline look.

    I just wonder what the thinking is at the moment

  8. Gravatar of Nigel BlackNigel Black
    Posted 01 September 2010 at 21:00:02

    Ref point 6, currently Pway are spending more time on maintenance of the existing line and only working on the extension as time and materials permit. We cannot afford to let a "charge" for Laverton deflect us from essential duties on the running line, otherwise we won't have one!

    Ref point 7, as for double tracking Winchcombe to Toddington, planned work on Chicken curve is to drop and slew track toward embankment centre, this would preclude re-instatement of double track here for the foreseable future.


Comment on this item