November 2009 S&T Report
article by: Andy Protherough
Week ending 7th November
Monday was spent loading the railcar and trailers with equipment
and materials for the week. Additional scaffolding to reach the top
of the new bracket signal at Toddington was the main priority, as
weather permitting, this week will see all the fittings to the
'above platform' posts being put in place. A medium sized cabinet,
two support legs and aggregate/cement, various pieces of angle iron
and the remaining signal fittings were also loaded.
After lunch a trip to Toddington saw additional under 'box work.
The electric lock coupling fitted to T29, and coupling bars fitted
to T7 & T19. A new cast token sign was fitted alongside signal
T24 (outer home).
Tuesday greeted us with very frequent and very heavy downpours
which made the task of bolting on fittings to the upper posts on
the bracket signal a very unpleasant one. By the time we stopped
for our 3.45pm tea break, approx 2/3rds of the fittings were up.
The remaining time was spent clearing the remaining fittings from
the gunpowder van so that this could be returned to Winchcombe.
No work was achieved on Wednesday/Thursday as our Head of
Department was bringing to a conclusion months of on/off house
moving by actually…… moving. We just await the house-warming party
invitations, or will trains running to Broadway come first?
Back at work on Friday to install locking in channels D & E
and to modify and fit a retaining bar under Toddington 'box.
Week ending 14th November
Monday gave Malcolm, John Simms and Danny Scroggins a day out in
Wrexham. Their task was to sort and load onto a waiting vehicle, a
selection of redundant lever frame parts for transporting back to
Winchcombe.
Tuesday saw us back at the Toddington bracket signal. First job
was to fit a lamp case to T29 (Stow side). A second for T27 has
still to be located. A double crank was then attached to the main
post approx. 3ft from the ground. This will direct the signal wire
pull from a horizontal direction to a vertical one. Once this was
in place the final alignment of the two signal wires could be
established and the remainder of the wire support stakes could be
concreted into place.
Whilst the concrete mixer was operational, a new concrete base
was built for the shunt signal (T31) at the base of the bracket,
and also the bracket access ladder was bolted to the platform and
its base concreted into the ground. The medium sized cabinet
brought from Winchcombe last week was also planted next to the
groundframe and concreted in.
The final job of the day entailed the re-routing of various new
signal wires around T28 (platform 2 starter).
Back at Winchcombe on Wednesday and a search amongst S&T
treasures for a good clean lamp case and a short access ladder for
T27 on the bracket. Both in need of some TLC! The inside of the
banner repeater casing received its first coat of white gloss, and
half of the lettering on a new token sign got the same
treatment.
Working under Toddington 'box again on Thursday, changing
couplings on T22 and to measure for electric lock coupling. A fault
that occurred on Saturday whilst the 'box was in operation,
required the tappet retaining bar for T25 to be filed for a better
fit.
Upstairs above the lever frame, measurements were taken of the
existing diagram to facilitate the alterations and additions needed
for a new version. A drawing was made of the block shelf for
Malcolm to work from for positioning the additional instruments
needed in association with the new signalling.
Mid-afternoon and back at Winchcombe, the electric lock coupling
was made for T22, the last of the token sign lettering was painted
white and a start was made on refurbishing a platform ladder for
T27.
Friday saw the platform ladder, support bar and hoop cleaned and
primed. A white surround was painted on the token sign, and
undercoat was applied to the banner repeater lampcase.
Week ending 21st November
Monday. The ladder for T27 bracket platform post, five assorted
support hoops, a cabinet door catch and two small 'shoebox' lids
are all painted with undercoat outside our coach at Winchcombe.
Alas, before the paint had started to dry, it began to rain, so a
hasty move to the MSC shed ensued. What pleasure it is to work
outdoors at this time of year!
Also, during the day the ten pallets of signal equipment that
had previously arrived from Wrexham were put into secure covered
storage with the help of Neil and the Loadall machine.
Tuesday. At Toddington today and myself and John P. are out with
the paintbrushes early to avoid the forecast late afternoon
showers/rain! The final top coats of white and black paint were
applied to the bracket signal, with the ladder being left untouched
with the hope that Neil would have time to finish all the
electrical connections……unfortunately time was not on our side! In
the gloom of late afternoon, a gravel path was laid around the back
of the signal to allow access to the ladder whilst avoiding
clambering over numerous signal wires.
Back at the signal box, Malcolm and Richard were busy
sorting/repositioning signal wires thru' wheel casts and fitting
vertical wheels under the lever frame for signals T13, T17, T18 and
T19. Once these were in position, two of the wires were jointed
into signals T17 & T19.
Wednesday. Malcolm and Neil spend much of the day under
Toddington 'box. The signal wire from T17 was joined to its
associated lever tail, a number of test pulls made and found to be
working satisfactorily. Further work was done on the locking trays
including fitting a coupling bar for T22 between the old & new
locking tray angles.
Thursday. The ladder for T27 previously undercoated now sports a
gleaming coat of gloss black paint along with its fixing hoop and
bar. While the black paint was out, the banner repeater case, two
hoops and four pivot casts were also treated. The afternoon rounded
off with the cleaning and greasing a total of five pivot casts.
Friday. A change of scenery sees Malcolm, Paul and Pete employed
at Kingsbury to repair damage to a hand operated point in the
yard.
Week ending 28th November
Monday. Due to the recent bad weather and the resultant amount
of rainfall, a decision was made to run the railcar from Winchcombe
to Toddington and back checking for any faults within cable joints,
especially those that lie buried in the ground. No major faults
were found, but a number of minor issues cropped up which will be
dealt with in the coming weeks.
During the afternoon, a drum of twenty pair and a drum of ten
pair cables were loaded onto a railcar trailer along with two ton
bags of ballast.
Tuesday. I, along with Richard braved the elements to drill and
bolt the short ladder to signal T27 on the platform of the bracket
signal. Once in place our final job was to fit a lamp case behind
each of the two spec plates. As soon as this was complete, Neil
connected the electric to each lamp back to the cabinet at ground
level. At last the scaffold tower could be removed to reveal a very
smart looking bracket signal that should see many years service. As
the last of the scaffold was removed, the final signal wire stake
was concreted into the ground adjacent to the bracket shunt
signal.
Over on the NHS siding, Malcolm and John P. were busy topping up
the ballast levels around the trap point and associated rodding
stools from the railcar trailer.
After lunch, four lengths of cable were run out. A 10 pair &
a 20 pair cable were run from the signal T20 cabinet to the
NHS groundframe cabinet, and a 10 pair & a 20 pair cable run
from the signal box to where signal T2 will eventually be planted
at the southern entrance to siding 1/loco yard. These final two
cables will be hand dug into a trench in the ballast to protect
them from the weather….a job for a cold winter's day.
Wednesday. From amongst our various bits of reclaimed steel
plates, two were cleaned and drilled in preparation for attaching a
motor signal mount. This will eventually adorn signal T32 at
Toddington, close to the viaduct where it will be too far to be
manually operated. The signal motor case and a pivot cast were also
cleaned. Seven speed-sign posts received a coat of black gloss.
Thursday. The finishing touches were made to the bottom bars of
the locking tray.
All that remains for me to say is a Very Merry Christmas to
everyone within the S&T Department who have achieved so much
this year, to all the volunteers on 'our'railway, and
to everyone else who is reading this report.
The next report (for December 2009) will appear during January,
so Happy New Year also.