June 2011 S&T report
article by: Andy Protherough
NOVEMBER 2010
The most part of November was taken up with the usual stripping
of parts, cleaning and painting within the confines of Winchcombe
yard. Over a two week period, the bracket signal outside of
Toddington signal box was stripped of its fittings, paint and rust
removed, and then given a fresh coat of red oxide followed by white
and black gloss paints. The fittings were replaced by 'stock' items
from Winchcombe, cutting down on the time taken to do the
refurbishment.
As a warming aid, the afternoon of the 23rd was spent
digging a trench in the ballast to bury three cables up to the
Toddington headshunt.
DECEMBER 201
Due to some early season snow and ice, Friday 3rd was
spent clearing packed snow and ice from around point blades, FPLs
and detection blades.
The remainder of the month (until 18th) brought more
refurbishing of parts and fittings. A general tidy up of our
storage containers was made to gather like-for-like items
together.
JANUARY 2011
Our first major task for the new year was to remove the ground
frame at Toddington North and replace with a motor point. This
required the removal of the FPL cast, stretcher bar and point blade
lugs from the main point before fitting the new main stretcher bar,
motor lugs and point blade lugs. A slight modification was needed
to the motor drive bar, requiring a little heating and bending.
Also in need of modification was the line of the point rodding.
This was disconnected from the ground frame and removed from the
rodding stools. Three of these stools needed slight realignment,
therefore needing to be dug out of the ballast along with two
concrete blocks with the angle crank. Once repositioned, point
rodding cut and reconnected, and the point motor connected to the
mains, then a test pull was made from the signal box......and all
O.K.
Wednesday 12th brought the unfortunate task of
removing all the bonding wires from the track around Chicken Curve.
This was in preparation for the P-Way Dept to begin track lifting
due to the infamous slip.
The next major task for the month was the 'planting' of the new
W36 post out on Chicken Curve, and the removal of fittings and post
from the old W36. The position of the new post on the opposite side
of the running line has been chosen because of the more stable
nature of the ground!
Tuesday 25th - removed all signal wire pulley casts
from their stakes around the 'slip' area.
FEBRUARY 2011
Apart from putting up new fittings on W36, most of the time has
been spent on restoration at Winchcombe. Malcolm has restored two
ex-midland region lamp cases to be used on refurbished distant
signals at Hailes in the future.
Towards the end of the month, Neil and Malcolm assisted P-way by
moving approx 160 sleepers back into position at Gotherington ready
for track laying.
MARCH 2011
The main task for this month is the reinstallation of signalling
equipment at Gotherington. Firstly, a medium size trackside cabinet
was refurbished to facilitate weatherproof cable joints along the
Gotherington loop. This required a total rebuild including interior
timber cladding and shelving. By the end of the month it was ready
for installing on the loop.
Also completed this month was the repainting of the distant
signals at Hailes. By the 28th, Malcolm and Neil had
replaced all the new fittings.
APRIL 2011
This month at last saw the repainting of W2 (south of tunnel)
which had been postponed from last year due to train operations and
the weather. Having an extra month of free line use has been a
bonus for us this year. By the 15th it looked as good as
new.
Middle of the month had the track circuits rebounded along
Gotherington loop, and new track circuit feed cables laid and
buried.
Three new concrete bases were constructed along the loop in
readiness for a disc signal and a couple of wheel plates.
On the 26th, myself, John P and Carl began a track
walk starting from T1 (Hailes) thru' to south end of Toddington
platforms. The task was to ensure all cables and point rodding
passing under the rails was visible and free moving. Almost every
cess (space between each sleeper) that carried either cable or
point rodding had to be cleared of ballast. New yellow tubes were
fitted around cables to make them more visible to the operators of
the tamping machine.
The long awaited repaint of Winchcombe signalbox has finally
been completed by the two Richards. Taking advantage of a very dry
spring, the box now looks very smart and is a credit to them
both.