April 2010 S&T report
article by: Andy Protherough
THURSDAY 01st.
The vertical wheel that had previously been stripped down and
had all traces of paint and rust removed, then repainted all in
between other jobs, was finally rebuilt and put into storage. This
will add to our 'stock' of wheels for the fitting out of Broadway
signal box. An afternoon visit to Toddington signal box with the
railcar to take measurements for making mid-locking tray fixing
bars. These will be made at Winchcombe before being fitted sometime
next week. Back onto the railcar for a trip south to Gotherington.
The purpose of this visit was to test the operation of the
motorpoint at the south end of the run round loop. All passed
O.K.
TUESDAY 06th.
All the lever lock covers were removed to make the task of hand
painting the appropriate signal numbers on each cover an easier
one. By early afternoon the last was painted and each one carefully
refitted to its lever lock. A refurbished large electric lock (for
signal T33) was drilled and fitted to its timber mount under the
lever frame.
Trackside jobs included applying an undercoat to the Annettes
Lock shed, and running a cable from this shed to the electrical
cabinet next to the banner repeater signal.
Whilst at Toddington, the ground under the Stow Road Bridge was
cleared and levelled to make room for a 'gardeners hut' to be
erected. This will allow the gardening staff secure storage for the
tools of their trade
WEDNESDAY 07th.
Following on from the refurbishment of the road crossing behind
C&W, a new warning sign for vehicle operators will be
installed. The reclaimed point rodding that will be used to mount
this sign was cut, drilled, cleaned and painted. A quantity of
angle iron was also cut and cleaned for use as an edging to
Toddington 'box locking tray, and a further two guide bars were cut
and filed to make 'check' position slots for Gotherington signal
G15.
THURSDAY 08th.
A mounting plate and contact box were removed from storage,
cleaned, drilled and fitted together. These will be taken to
Gotherington 'box and fitted to the FPL (Facing Point Lock). The
electric lock was dismantled to enable a thorough clean of the bar
and contact box couplings. The angle iron cut yesterday was drilled
ready for fitting.
An afternoon visit to Screwfix and Leyland paint shop resulted
in some general housekeeping chores sorting and storing new bolts,
nuts, washers, spanners, wire rope, thimbles and paints…..should
keep us going for a while!
FRIDAY
09th.
A trip in the railcar to Gotherington to fit the above mentioned
guide bars to G15 on the locking tray. This was followed by
checking and stripping down G7 lock and removing G10 guide bars.
These were all taken back to Winchcombe where new check positions
were cut in the guide bars, a new contact block fitted to the
contact box and cut new contact box coupling bars.
After a late lunch all the above were returned to Gotherington
where the guide bars were refitted and G7 electric lock was
rebuilt.
TUESDAY 13th.
After standing at the end of platform 1 since end of March
looking ghostly in its undercoat, the Annettes Lock shed finally
had a coat of gloss paint applied. To match other platform
furniture around it, the trim was painted in a caramel colour,
while the main body was painted a light stone. During the afternoon
our painting skills were applied to five line side electrical
cabinets, with a fresh coat of aluminium silver.
WEDNESDAY 14th.
A second coat of light stone gloss was applied to the Annettes
Lock shed, followed by a coat of black gloss to the lids of the
five electrical cabinets painted yesterday.
THURSDAY 15th.
Undercoated six sign brackets (ex point rodding), and one
electric lock cover. A quick trip to Toddington in the railcar to
repair AJT section track circuit feed, then to Gotherington to
repair three track circuit feeds, black gloss bracket and detector
cast, and to dismantle/cut a lever leg and bar.
Dad (John P.) and I spent the day erecting a new fence at
Gotherington station in preparation for the GWR 175 Gala. This just
goes to show the diversity of tasks one can get involved in on
'our' railway!
FRIDAY 16th.
Malcolm assisted with a morning of shunting wagons around
Winchcombe yard, followed by applying black gloss to the six sign
brackets. After lunch it was off to Toddington to finish the
mid-locking tray bars and covers, then fitting T33 lever leg and
marking up for modifications. Neil fitted the Annettes Lock into
the shed and electrically connected back to the signal box.
MONDAY 19th.
A second coat of caramel gloss was applied to the Annettes Lock
shed and a coded door lock fitted. This now completes this project
ready for our trains to Laverton and beyond.
Back at Winchcombe, the new sign for the road crossing behind
C&W was erected, and an assortment of palletised fittings moved
and sorted for storage/restoration. Both railcar trailers were
unloaded of signal posts and concrete blocks recovered from
Gotherington.
TUESDAY
20th.
After the dreadful report of a possible land slip on the
Gotherington loop, an immediate inspection was carried out this
morning. Not a good day out! By 'prodding' the ballast with a six
foot bar in between the sleepers, the horrible sight of this bar
disappearing into a void was not what we had expected. The details
can be read elsewhere on www.gwsr.com
After a 'shock-recovery' cuppa, the chance was taken to have a
general tidy up in and around the signal box. After lunch, an old
cable run from the Dixton cutting to Far Stanley was pulled out of
the ballast, cut into approx. 12 foot lengths, and put onto the
trailer. This will then be sold for scrap.
WEDNESDAY 21st.
The job of unloading the railcar trailers was the primary
objective for today. Scrap metal had to be kept separate from scrap
cable, from scrap timber, etc. This took up most of the
morning to achieve.
The afternoon was spent cleaning a signal detector assembly and
contacts, before reassembling.
THURSDAY 22nd & FRIDAY
23rd
Both days spent at Winchcombe using the trusty angle grinder
with steel wire brush to remove layer upon layer of paint from
numerous fittings including such items as hoops, brackets, post
angles, balance weight arms, balance weights and ladder support
brackets. Once thoroughly cleaned, first a coat of red oxide was
applied, then an undercoat. In total, approximately 35 different
fittings were worked on over the two days.
SATURDAY 24th
Six lineside electrical cabinets between Toddington signalbox
and Hailes Bridge were rubbed down and given fresh applications of
black and silver paint. At some point during the summer, the
intention is to spend some time removing weed growth from around
each cabinet, and build a concrete base so as to reduce maintenance
and ease access.
MONDAY 26th
One of the motor points in store has been moved undercover and
near to our work area to be checked over and for any repairs to be
carried out. This will then be used on the North Headshunt siding
in place of the current groundframe, another job for the
summer!
At the same time, a signal post for the replacement W36 (chicken
curve) was brought out of storage and placed where it can be
refurbished with relative ease.
A number of wooden sleepers and decking timbers were taken to
Gotherington for the installation of a new foot crossing at the
south end of the platform in preparation for the GWR 175 Gala.
And another batch of fittings was treated to a clean with the
grinder and wire brush.
TUESDAY 27th.
Three more lineside electrical cabinets were freed from weed
growth and given a fresh coat of black and silver paint. Another 20
or so fittings had the wire brush treatment, while a rather
stubborn signal post angle crank was freed up. Unless regularly
greased/oiled, these rather tight fitting items can soon become
seized solid, and since this one had stood idle out in all weathers
for many years, had done just that. But with copious amounts of
penetrating fluid and gentle persuasion with a lump hammer will
usually come free.
A new delivery of single wheel wire casts were paired with the
necessary nuts, bolts and washers ready for use.
At Toddington, John P, Carl Smart and I laid a new telecoms
cable from the station masters office to a cabinet in the bay
platform. This will be connected by Neil and hopefully return
normal telecoms from the signalbox to the office.
Further up the line, a non-slip mesh was tacked to a small foot
crossing over signal wires near to the ground frame, a small
request from the rail inspectorate.
WEDNESDAY 28th.
Another batch of fittings for cleaning included downrod
brackets, spec plates and signal post angle crank. A total of 15
were worked on today.
THURSDAY 29th.
Today the task of painting the numerous fittings cleaned over
the past week began. Firstly, red oxide, followed by undercoat and
then either white gloss or black gloss.
After measuring the signal post for W36, a ladder was sourced
from storage along with a crows nest and top-end fittings. Along
with the post, the crows nest and ladder are in need of
restoration.
FRIDAY 30th.
Another day of painting fittings at Winchcombe.