March 2006 Progress report
article by: John McMillan
Writing this piece in March which is proving to be decidedly
wintry, we hope for better working conditions soon, as handling
freezing cold tools and materials is not much fun. Despite this
we've seen good progress on the boiler cladding, which has occupied
many man-hours to get to its present position.
The boiler barrel is clad with four complete steel sheets, each
ring being split into two semi-circular sections. The join lines
run along the top and bottom of the barrel. Six of the eight sheets
are in position on the boiler and looking good. Although the sheets
are rolled to the diameter of the boiler, making the cladding isn't
as simple as wrapping sheets around a cylinder, as the front
section of the boiler is tapered. Even the taper is not a simple
geometric cone; the top of the tapered section is roughly in
alignment with the parallel rear portion, whilst the underside
tapers upwards quite steeply, giving a distorted cone. It's not
just the tapered shape that complicates the cladding, as on the
underside of the front section of boiler there has to be a flat
section to accommodate the inside expansion link, part of the valve
gear. Even then there is not much clearance. Also because of the
taper, the sand box filler pipes are very close to the boiler and a
recess has to be cut in the cladding to prevent fouling by the
pipes. An additional clearance has to be made to allow for boiler
expansion which is approximately ¾" (20mm) when up to temperature.
So you can understand why the job is taking so long!
The sections of cladding around the manifold shut-off valve and
the shoulder for the front right hand side of the firebox have been
completed. The sand pipe deflector plates have been made up. These
fit round the sand box filler pipes and are intended to stop spilt
sand finding its way into the moving parts of the loco. The plates
still need to be welded to the running boards.
With three quarters of the barrel cladding in place we took the
opportunity to offer up to the barrel the nameplate plinths, which
were made up some years ago. Locating them correctly has been
a challenging exercise as there is no local datum point from which
to take a measurement. There was much adjustment and lively debate
before all were satisfied that the plinths were at the correct
height, and horizontal in relation to the barrel and running
boards.
Both outside cylinders have been completely de-rusted and have
received several coats of paint. After taking advice from other
locomotive groups, and undertaking much research, we have selected
what we hope will be a suitable lagging material for the cylinders.
This is a laminate of aluminium sheets and insulating material, and
appears to be suitable for our needs. We've made small pads to fit
in all the spaces and hope it will work successfully. Who would
have thought we'd need dressmaking skills on a Merchant Navy? Once
this is fitted, the cylinder cladding can go on for what we hope
will be the last time.
The floor of the smoke box is sacrificial, and we have removed
the last section of plate from in front of the tube plate. We have
welded the smoke box door sealing-ring into position. This
ring provides a surface against which the door closes to form an
airtight seal. We will now be able to correct the alignment of the
smoke box door and get it to close properly.
In the machine shop we have managed to make progress on a number
of tasks. The dome-headed pin for the tender-end of the drawbar has
been finished off. The support for the handbrake handle has been
re-machined to remove wear and corrosion, prior to making the
vertical shaft that operates the brakes. Castings have been
obtained for the brake hangers; these arms hang down either side of
the tender wheels and provide a mounting for the brake blocks. The
original parts would have been forged, but we have opted for steel
castings.
We have taken delivery of six ends for the three tender vacuum
reservoirs, which are mounted prominently on the rear deck of the
tender tank under a steel cover. The tank ends are dished to
withstand the pressure, and have been produced by a process called
'metal spinning' which forms the required shape in the metal
without applying any heat.
Finally, at last we are giving serious thought as to how best we
can fit out and complete the boiler. This is the last major
fund-consuming item in the restoration of 35006. Plate work repairs
and fitting of a new firebox tube-plate were carried out nine or
ten years ago, but there is still a long list of jobs requiring the
services of a skilled workforce, and we have no choice but to
contract this work out.
We have nearly sufficient funds to re-tube the boiler, but to
get to the stage of hydraulic and steam tests (and the start of the
ten-year 'ticket') we are going to need some serious money . If you
would like to help us overcome a major financial hurdle in the
restoration of this magnificent locomotive, and make significant
progress towards completion, just send an e-mail with your name and
address to 35006@gwsr.com. Full
details of how you can contribute will then be sent to you.