July 2007
article by: Paul Fuller
On the first weekend of this rather soggy month (7th July), the
P-way gang were back at Hunting Butts Cutting (Cheltenham RC) to
continue with the new siding being laid for the storage of wagons.
The work was completed and saw the existing headshunt disconnected
and slewed over to connect with the new siding. Bets were being
taken by the gang to see how long it would take before the siding
was full of "long term restoration projects", and the answer was…
just two days later! Oh well, that's what we're here for!
The following weekend saw the gang back up on the northern
extension inching ever closer to Broadway. A total of 241 concrete
sleepers were laid out which equated to about 10 panels of track
and, at 60ft a panel, that's 600ft - or 182 metres - towards our
goal.
In the week that followed we all heard about and experienced the
immense flash flooding that occurred and our railway too suffered
the brunt of the weather. On Friday the 20th of July it was
reported that a steam fire and drive course had to be cancelled and
reports were received of major flooding of the railway's
infrastructure. There was nothing we could do except ride it out
and let Mother Nature take her course. On the Saturday morning two
members of the P-way department, along with our Operations
Director, took a track possession out and headed slowly down the
line on the '73' to inspect any damage caused to the railway.
Between Toddington and Winchcombe all seemed ok. A few drains were
overflowing, but the water level had dropped significantly and was
flowing fast and more importantly freely through the culverts
around the bottom of the embankments. All was not well at Dixton
however. Part of the embankment near the road-over-rail bridge had
slipped and was precariously close to the track but not over it.
The decision was made there and then not to run trains until this
was sorted out. Fortunately being a narrow-bodied design, the 73
was just able to squeeze past the slip and continue towards the
Racecourse. Some further storm damage to the formation through
Bishops Cleeve was noted but wouldn't affect any train running.
With no further major damage evident, the loco set back to
Toddington whilst P-way, along with the JCB, attended to the
embankment slip at Dixton.
After moving several tonnes of earth, we moved down to Bishops
Cleeve and levelled out the gorges scoured out by the storm and put
everything back to normal. Whilst our damage was not on the scale
that the Severn Valley Railway have suffered, it is incredible what
the forces of nature can do!
In the afternoon we headed up to Stanton to lay out twelve rails
(six pairs) on the sleepers laid out the previous week before
finally calling it a day. The railhead is now just north of the 8
mile-post. Toddington Station is 9m40ch, so we're a long way from
home - a mile and a half to be exact!
The final weekend of the month saw the gang continue working on
the nortThe northern extensionhern extension where the twelve rails
laid out last weekend were clipped to the sleepers as well as an
additional three more pairs of rails being laid down and secured to
the sleepers. Looking back south now, the Stanton Road bridge is
almost out of sight whilst looking north the B4632 road bridge is
now getting ever closer! All we need is for the bridge repairs to
be completed before we reach it, otherwise we'll have to leap-frog
around them!