Carriage & Wagon Report August 2006
article by: Richard Johnson
July has been a month of steady, if unspectacular progress. Once
we were able to put the FK (Corridor First) 13329 into use in the
Carmine & Cream set, that rake was used on the Thomas weekend
for the first time, as three full sets were required.
The benefit of having three serviceable sets was immediately
apparent. Some jobs needed doing on the Chocolate & Cream set.
It was therefore decided to leave the Carmine & Cream set in
use for a couple of weeks whilst we sorted those problems out at
Winchcombe.
It has proved to be a very useful period, because it has given
us an opportunity for the first time to do some work on the
Chocolate & Cream rake, that otherwise would have had to wait
until the Winter shut down. For example, all dynamo belts have been
adjusted, and one has been replaced. All brakes have been checked,
and a worn vacuum hose has been replaced.
Also, since the TSO (Tourist second Open) 4772 was refurbished
last year, the steam heating has not worked properly. There has
been a bad steam leak underneath, and the coach did not warm up
properly. By having time to make a proper investigation, we found
that a section of pipe work had corroded and split. This was not
allowing steam into the pipes feeding the interior. The offending
section of pipe has been removed - not without some effort - and
has been repaired. None of this would have been possible if the
coaches had been in use.
Work has continued steadily on the other TSO 4763, whilst all
this was going on. The plan is to have it operational by next year,
so everything that is being done to it at the moment is a bonus.
One side is painted up to undercoat stage, and the other is well on
the way. A section of badly corroded vacuum pipe has been removed
from underneath, and this necessitated first stripping everything
out of the toilet, and then removing the toilet floor to gain
access. That was a first for us. The pipe which was removed was
found to have several large rusty holes in it, so there was no
chance of repair.
We were also fortunate to find that another Mk 1 TSO 5042
(pictured right) was delivered to Toddington in July. The owner
offered it to us in exchange for an old Mk 1 CK (Corridor
Composite) which has been on the railway for about 20 years, and to
be honest was never going to be restored. The agreed plan was to
strip the CK of everything useful, and then send that for
scrap. Stripping internally is now complete. We have now
started on the bogies. The coach was lifted on our jacks last
weekend, and everything worth salvaging from the bogies will be
removed, before the coach goes for scrap.
5042 is one of the last TSO's to be built. It has the melamine
interior, and is overall in a very good condition save that
virtually all windows were either broken or missing. Someone has
got to it before us, and removed all the pairs of double sliding
windows and the doors. We are in the process of replacing the large
passenger windows. Rubber surrounds hold the windows in, and a
supply of that has been sourced. We already have enough large
windows in store. The plan immediately is to make it watertight for
the coming winter, and then restore it shortly thereafter, to go
into the Maroon rake. It is in a better condition, and is far
more complete than 4865 which was purchased a couple of years ago.
You will see a picture of it here, with most of the windows
replaced, and hardboard covering others.
Work has been continuing on the 1928 GWR tool van, No. 4. A
contractor was located who could replace the roof covering. The
owner agreed, and the work was completed last week. Work on the
vehicle is progressing well, and it is already looking very smart
in GWR chocolate with bright red ends, and yellow lettering. We had
a fairly major shunt last weekend, and I took the opportunity for a
photograph whilst it was temporarily outside.
The Carmine & Cream set is now at Winchcombe for a couple of
weeks, for some remedial work to a couple of coaches. One or two
need running repairs to the upholstery. Once these jobs have been
done, it will go back into use and we shall take the Maroon set out
for refurbishment.
Finally, after discussions with members of our diesel
department, plans are in hand to borrow a steam boiler for location
at Winchcombe. The plan is to refurbish one of the spare ex-diesel
steam boilers, and locate it at Winchcombe adjacent to our carriage
shed. When overhauled and plumbed in, it will mean that we can lift
a carriage off its bogies, check for steam leaks and carry out
repairs before returning the coach to use; something that has been
impossible to date. Thanks are due to the owners of the boiler for
allowing us to borrow it for this purpose.