Carriage & Wagon Report April/May 2006
article by: Richard Johnson
The last few weeks has been one of those periods when although a
great deal of work has been done, we do not seem to have too much
tangible to show for it. The one vehicle which has been out shopped
is the BR Standard box van No.772065, which is shown in the top
photo. The majority of the work on this vehicle was done by
Grenville Care, and a fairly derelict wagon has been turned into a
useful asset. It is fully fitted, so is available to run, and may
be seen operating in our forthcoming Gala. It is impossible now to
tell that all four doors are brand new, and replaced four rotten
and broken ones that previously only partially closed.
Work has continued steadily on the FK (Corridor First) 13329.
All the exterior body painting is finished save for a small amount
under the solebar. Three of the seven compartments are now
complete, and the other four are well advanced. The replacement of
all fittings in each of the compartments is a slow and laborious
task. Each item has to be matched up, and fitted in sequence. Many
of the items of trim are small and fiddly, and inevitably some go
missing or for some reason simply fail to fit back where they
obviously came from.
A significant proportion of the trim has to be made up, as it
was damaged or missing when we began work. That is particularly
true for example of the veneered panelling under the window. If (as
so often happens) water gets in through a broken window seal, then
this is the first part to suffer from rot. New panels have had to
be made up and fitted in all compartments. Because originally the
seven compartments were fitted with strikingly different veneers,
this has led to much experimentation with various wood stains to
try and ensure that so far as possible, the new exactly matches
with the old. The best check that this has been achieved is
confirmed by the fact that most people don't notice that the panels
have been completely replaced.
When British Railways began construction of the Mark 1 coaches
in the early 1950's, it was decided to fit all interiors with
'Empire hardwood' veneered panelling. Apparently, at that time just
after the war timber from various parts of the British Empire was
readily available, so the decision was made to use it. In many of
our coaches you will find small embossed panels naming the precise
wood used for the veneered panelling. This is an original feature
which we have retained as far as possible. What is very interesting
is that often in one coach, such as in 13329, several totally
different veneers were used in adjoining compartments. It would be
very interesting to know just how the choice was made, unless it
was just completely random.
Once all compartments are complete, the moquette seat covers
will be given a thorough clean with our industrial shampooing kit.
That should bring them up as good as new. Happily, the moquette
itself is in very good condition, and should give a number of years
service.
The toilets still have some work to be done to them, including
in particular the replacement of all plumbing (most of which had
been stripped out before the coach arrived). Although estimating
finish dates has historically shown itself to be a dangerous
occupation, we reckon that the coach is about four weeks away from
being completed.
More work has been undertaken on the BR Standard Brakevan No.
B954962. But this now needs serious attention by the carpenters,
and they will need to finish all woodwork on the FK before they
turn to this. All the rotten timber has been removed, and new has
arrived to replace it. Once the new cladding starts to go on, it
will begin to look as good as new. The photo above shows the extent
of the work necessary. A GWR Tool and Breakdown van No. W4 is
lurking behind it. Work has just started on that. More about that
another time.
After all our many months of hard work, our RBr 1675 went into
service over the weekend of the Diesel gala and was an instant
success. Our OTC department bought enough bacon for bacon
sandwiches for the weekend (so they thought). They sold out on the
first day! That indicates the potential.
We have had to take the vehicle back out of use for a couple of
weeks, to deal with a number of 'snagging items', which was only to
be expected. The most serious were an emergency door which would
not close properly, and a problem with the lights. Others, were
much more minor such as a couple of leaking water pipes, bolts
needed on a couple of cupboard doors and a shelf required for the
till. The gas powered generator played up on one day, and somewhat
frustratingly since then it has worked perfectly. All efforts to
replicate the fault to find out what was wrong, have failed.
Hopefully the coach will be back in action in a week or so. At the
time of writing this, all defects have virtually been cleared.
As was mentioned in the last report, once the FK 13329 is
finished, that will give us five Carmine & Cream coaches, which
with a spare Chocolate & Cream SK 25452, will allow us to make
up another rake of six. That we intend to do, as it will allow us
to withdraw the maroon rake for some repainting and refurbishment.
Many of the maroon coaches have been in use for a number of years -
of necessity, and are now looking a bit 'tired'. There are also a
number of items in several of them that require rather more
attention then can be given by our midweek 'light repair' gang.
For the first time ever we shall have three full rakes of
coaches, which will allow a degree of rotation for repairs and
servicing. What unrivalled luxury that will be..